There was NO construction update this past Friday, October 10; however, there were some new developments this past week:
A temporary wall was put in place by the Chefs’ office in the Bistro Lounge.
The Chefs—Eddy, Sherve, and Deigo—moved temporarily to the computer room located right outside of the Gathering Room. Demolition will begin on Monday, October 13, in the Chefs’ office and only that office. No other part of the kitchen will be demolished, as of yet.
The temporary kitchen was inspected and cleaned.
The stairs by the entrance to the Formal Dining Room will remain open.
The next construction update will be on Friday, October 17.
Information from the office of Ellen Ottstadt.